Quad Stack — 20 ft standard DC block

Two 2×2 clusters with skids stacked between them — eight DC blocks sharing a central aisle

Overview

Two 2×2 clusters side by side with two PCS & MV skids stacked vertically between them. Each skid serves one row from both clusters — four blocks total.

PCS & MV skid
Quad Stack — two clusters, skids stacked in center
ParameterValue
DC blocks8 × 20 ft (two 2×2 clusters)
PCS & MV skids2 × 40 ft
Section height7.9 m (25.8 ft)

Energy capacity

At 2h each skid would need to convert more power than it can handle, so the solver builds Quad Split pairs instead.

DC blockBESS section (8 blocks)Duration
6.25 MWh50 MWh / 12.5 MW4h

Clearance and spacing defaults

Service clearance and spacing used by default. All values are adjustable in BESSLayout.

SettingDefault
DC block door side3.5 m (11.5 ft)
DC block cable end2 m (6.6 ft)
PCS & MV skid3 m (9.8 ft) all sides
Fire separation (between DC blocks of different sections)5 m (16.4 ft)

Cable layout

Each skid serves the row nearest to it — the top skid connects to the top row of both clusters, the bottom skid to the bottom row. At 40 ft each skid has two PCS sections.

Single BESS section footprint

Land area at default clearance. Door clearance on the top and bottom (outward-facing doors), cable-end clearance on each side.

Doors facing outward

Skids in center, DC block doors top and bottom

664 m²(7,143 ft²)
47.8 × 13.9 m
156.9 × 45.5 ft
Land useValue
Footprint47.8 × 13.9 m (156.9 × 45.5 ft)
Total area664 m² (7,143 ft²)

Multiple BESS sections footprint

Land area for four sections, in a row and in a 2 × 2 grid, at the default spacing.

Clearance
4 × 1 grid

4 sections · 32 DC blocks

2696 m²(29,020 ft²)
194.3 × 13.9 m
637.5 × 45.5 ft
2 × 2 grid

4 sections · 32 DC blocks

2392 m²(25,750 ft²)
96.6 × 24.8 m
317.1 × 81.2 ft